Construction of Infrastructure Works for Reclamation of Zone K & L (400,000 Feddans)

El-Dabaa Corridor / Mostakbal Masr

Flow Serve Role: Construction Partner

Client: SIAC S.A.E Main Contractor : Future of Egypt for Sustainable Development Authority

Duration: 4 Years

Completion: on going

Capacity: 400,000 FEDDANS

Scope of Work:

  • Construction and Installation
  • Hydro-Testing and Commissioning
  • Maintenance
  • construction of all networks & pumping stations to irrigate 400,000 feddans
  • Supply, Fabrication, Painting & Erection of:   

    Networks to be installed include the following:     

    - Prestressed pipeline length 29 km in diameter (1200mm to 2500mm)

    - Steel pipeline length 148 km in diameter (1200mm to 3000mm)

    - HDPE pipeline length 255 km in diameter (200mm to 1000mm)

    - UPVC pipeline length 300 km in diameter (200mm to 315mm)